Italy has activated its definitive FER X mechanism, under which 10 GW of new photovoltaic capacity will be allocated through competitive auctions. The scheme is part of a broader programme supporting a total of 37.15 GW of new renewable energy capacity by the end of 2030.

On 10 August, Italy’s energy services agency GSE published the operational rules for implementing the mechanism following their approval by the Ministry of the Environment and Energy Security. The decree entered into force on 7 August after previously receiving approval from the European Commission.

Most of the capacity will be allocated through auctions

Of the total capacity covered by FER X, 27.15 GW will be allocated through competitive procedures for plants with a capacity above 1 MW. A quota of 10 GW has been set for photovoltaic plants, while 16.5 GW has been allocated to wind power.

The auctions will also support 630 MW of hydropower and 20 MW of plants using gases generated by wastewater treatment processes. GSE plans to organise the first auction by the end of 2026, followed by another two procedures during 2027.

In addition to the auction mechanism, a further 10 GW is reserved for plants with a capacity of up to 1 MW, which will be able to access support directly. This quota is not reserved exclusively for solar energy but applies to all technologies covered by FER X.

Stricter conditions for large solar projects

Photovoltaic projects with a capacity above 1 MW must hold a final construction and operating permit before participating in the auctions. Registration in Italy’s GAUDÌ system and an accepted grid connection offer will also be required.

Projects will first undergo a qualification procedure conducted by GSE before they can participate in competitive bidding. A reference price of €80/MWh has been established for solar energy, although the final price awarded to each selected project will depend on the auction results.

Price adjustments are also envisaged for certain types of projects. Photovoltaic plants replacing asbestos roofing may receive an additional €27/MWh, while solar installations built on water surfaces could receive a premium of €10/MWh.

Support through two-way contracts for difference

The principal support model will be two-way contracts for difference. When the wholesale electricity price is lower than the price awarded at auction, GSE will pay the difference to the producer. When the market price is higher, the producer will return the difference.

Through this mechanism, Italy aims to provide investors with predictable revenues while protecting consumers from excessive payments during periods of high market prices. The scheme covers photovoltaic, wind and hydropower plants, as well as a limited category of installations using gases generated by wastewater treatment processes.

European Commission approves €23 billion support scheme

In June, the European Commission approved the Italian scheme under European Union State aid rules. The mechanism’s total budget is estimated at approximately €23 billion, while the supported plants are expected to add capacity equivalent to around 48% of Italy’s current installed renewable energy capacity.

FER X will remain in force until 31 December 2030. However, the direct-access mechanism could close earlier, namely 60 days after plants of up to 1 MW reach the combined quota of 10 GW.