Eurowind secures grid connection approvals for 2.3 GW in Romania

September 3, 2026

Eurowind Energy Romania has obtained technical grid connection approvals for seven renewable energy projects in Romania with a combined planned capacity of 2,307.4 MW. The projects include wind farms, a solar PV plant and a battery energy storage system.

The approvals, known in Romania as Avize Tehnice de Racordare (ATR), were obtained in June 2026 and represent an important step towards the future connection of the projects to Romania’s national electricity system.

However, this does not mean that construction will begin immediately or that all the necessary permits have already been secured. The projects are scheduled to connect after 2030, while their completion will depend on further reinforcement of the electricity grid and the timely acquisition of construction permits.

This was stated by Adrian Dobre, Country Manager of Eurowind Energy Romania, in the company’s official announcement.

According to Dobre, obtaining technical grid connection approvals for an additional 2,307.4 MW represents an essential step in expanding the company’s project portfolio. He noted that Eurowind is working closely with grid operators and public authorities, but that the connection and completion of the investments will depend on the necessary grid reinforcements and construction permits.

Largest project is a 1,188 MW wind complex

The largest of the seven projects is planned in Botoșani County and is expected to reach an installed capacity of approximately 1,188 MW.

The project involves the phased construction of nine wind farms at different locations across the county. According to the timetable published by the company, implementation is expected to begin around 2031.

The second-largest project is the 900 MW Albești wind farm in Constanța County.

The portfolio covered by the technical grid connection approvals also includes:

  • Mănești in Prahova County – a 49 MW project combining a solar PV plant and battery energy storage;
  • Stăncuța in Brăila County – a 49.6 MW wind farm;
  • Liești in Galați County – a 49.6 MW wind farm;
  • Slobozia Conachi in Galați County – a 49.6 MW wind farm;
  • Pechea in Galați County – a 21.6 MW wind farm.

Development pipeline of approximately 7.5 GW

Eurowind Energy Romania currently has a development pipeline of approximately 7.5 GW at various stages. The company has already started construction work on the Frumușița and Vector wind farms in Galați County and the Pecineaga North-East project in Constanța County, with a combined capacity of 138 MW.

Eurowind has been active in the Romanian market since 2011. It operates four solar PV plants in the country: Hălchiu, Măgurele, Pufești and Teiuș, as well as the Pecineaga wind farm.

The company has 184 MW of operational capacity in Romania, including a 60 MW battery energy storage system at Teiuș.

The ATR approvals provide the technical pathway for future grid connection, but they do not constitute final construction permits. The main challenge facing the entire 2.3 GW portfolio remains the timely expansion and reinforcement of Romania’s electricity grid.