US Department of Energy backs 84 grid projects

October 15, 2026

The US Department of Energy (DOE) announced plans on 13 October 2026 to support 84 projects aimed at modernising and expanding electricity transmission and distribution infrastructure across eight US states. The projects will be implemented by the Tennessee Valley Authority (TVA) and local power utilities.

The projects have a combined value of approximately $581 million, including $250 million in planned federal funding. The remaining $331 million will be provided through matching contributions.

According to the DOE, the investments are expected to unlock approximately 2.5 GW of additional grid capacity, improve electricity supply reliability and reduce constraints across existing power infrastructure.

Grid modernisation across eight states

The projects form part of the Resilience Amplified: Multi-Market Grid Interconnection Initiative, supported through the federal Grid Resilience and Innovation Partnerships (GRIP) programme.

The initiative covers investments in transmission and distribution infrastructure designed to improve the utilisation of existing grid assets, reduce electricity transmission congestion and strengthen system resilience during power disruptions.

According to DOE estimates, the investments are expected to improve electricity reliability for approximately 2.58 million homes and businesses. Project implementation is also expected to support around 800 jobs.

The Department emphasises that expanding grid capacity is essential to meeting growing electricity demand, particularly in areas where economic development and new investments are placing additional pressure on existing infrastructure.

Combined with SPARK, planned investments reach $741 million

The new funding announcement builds on TVA’s earlier selection under the Speed to Power through Accelerated Reconductoring and other Key Advanced Transmission Technology Upgrades (SPARK) programme.

Under this programme, TVA plans to modernise approximately 125 miles (201 kilometres) of existing transmission lines in Tennessee, Alabama and North Carolina.

The $159.7 million project involves the deployment of advanced conductors and grid management technologies, which are expected to increase transmission capacity by approximately 1,900 MW.

Combining the GRIP and SPARK programmes brings TVA’s total planned grid investments to nearly $741 million, including approximately $329.8 million in federal support.

Together, the two programmes are expected to unlock more than 4,300 MW of additional grid capacity.

A central element of this approach is increasing the capacity of existing transmission lines through modernisation rather than relying exclusively on the construction of new transmission corridors. Such upgrades can improve the utilisation of existing infrastructure and help reduce grid constraints.

Funding remains subject to final agreements and approvals

Although the Department has announced its support, the projects do not yet represent fully contracted or unconditionally approved investments.

The final amount of federal funding, project scope, implementation schedules and other conditions will depend on the execution of agreements with the DOE and the completion of the necessary environmental, administrative and regulatory procedures.

The investments form part of broader US efforts to expand electricity infrastructure and improve grid reliability. As electricity consumption increases and new generation, industrial facilities and digital infrastructure are developed, the ability to deliver electricity to consumers is becoming just as important as building additional power plants.

ECI