The Government of Republic of Serbia has adopted amendments to the Regulation on Conditions for Electricity Delivery and Supply, effectively postponing the connection of new electricity producers from variable renewable energy sources until 2029.

Under the new amendments, grid connection studies for all applications submitted before the Regulation enters into force will only be prepared in the period from September 1 to December 31, 2029. In practice, this means that Serbia is delaying the connection process for new solar and wind power plants by almost four years.

Previous amendments adopted in 2025 had envisaged that connection studies would be prepared between July 1 and October 31, 2026, but the new decision significantly shifts the timeline.

The move comes at a time when the Serbian power system is facing growing pressure from the rapid expansion of renewable energy projects, particularly regarding grid stability, balancing requirements, and the limited capacity of the transmission and distribution network.

New Framework for “Active Customers”

The amendments also introduce a new regulatory concept for so-called “active customers” consumers who install their own power plants and/or battery storage systems, with the possibility of injecting surplus electricity into the grid or providing services to the power system.

To obtain active customer status, the power plant must have an installed capacity of at least 150 kW, while its capacity cannot exceed the approved connection capacity for electricity consumption.

Significantly Higher Financial Requirements

The new regulation also introduces stricter financial conditions for investors.

For connection studies related to power plants up to 50 MW, investors will have to provide a financial deposit of EUR 50,000. Additional fees apply for larger projects:

  • EUR 400 per MW for power plants up to 100 MW,
  • EUR 300 per MW for projects between 100 MW and 250 MW,
  • EUR 200 per MW for each MW above 250 MW.

After obtaining the connection study, investors must also provide a bank guarantee of EUR 12,500 per MW of installed capacity for the power plant or energy storage facility.

If a new consumer facility is being built without a power plant and/or battery storage system, the bank guarantee amounts to EUR 25,000 per MW of approved consumption capacity.

For power plants producing electricity exclusively for self-consumption, without injecting electricity into the grid, no bank guarantee is required.

Two Annual Application Windows

The amendments introduce fixed application windows for connection requests:

  • January–February,
  • July–August.

Connection studies will be prepared in two annual cycles:

  • from March 1 to June 30,
  • from September 1 to December 31.

Potential Curtailment of Renewable Generation

According to the Regulation, based on the results of the connection study, the system operator may impose temporary active power limitations on power plants with installed capacity above 200 kW.

The limitation may reach up to 30% of the approved capacity, but no more than 5% of the facility’s total annual electricity production.

This represents a clear signal that the future development of renewable energy in Serbia will increasingly depend on the availability of grid infrastructure, system flexibility, and the deployment of energy storage capacities.

Collective “Active Customers” in Residential Buildings

The Regulation also introduces the concept of a “Group” multiple consumers within the same building jointly acting as a single active customer.

The members of the group will bear joint responsibility for obligations arising from the construction, operation, and use of shared power plants and/or battery storage systems.

The new amendments represent one of the most significant regulatory interventions in the Serbian electricity market in recent years and further raise the question of whether the region’s power infrastructure is prepared for the accelerated integration of large volumes of variable renewable energy sources.

Source: oie.rs