Preparatory works are expected to begin in the coming months, while the loan agreement with JICA is planned to be signed during EXPO 2027
Serbia is entering a new phase in the development of the Bistrica pumped storage hydropower plant, one of the country’s most important strategic energy projects. Preparatory works are expected to begin in the coming months, while the tender for construction of the main plant is planned for 2027.
The announcement was made by Serbia’s Minister of Mining and Energy, Dubravka Đedović Handanović, following the seventh meeting of the working group responsible for the project’s implementation.
According to the official statement issued by the Ministry of Mining and Energy, work is underway on the technical and tender documentation, the resolution of property issues and coordination with the Japan International Cooperation Agency – JICA.
Planned capacity of approximately 660 MW
The Bistrica pumped storage hydropower plant is designed with a total installed capacity of approximately 660 MW. The Ministry lists expected annual electricity generation of around 1,600 GWh.
For a pumped storage facility, this figure refers to electricity generated in turbine mode. The plant first consumes electricity to pump water into the upper reservoir before releasing the stored water through turbines and returning part of that energy to the grid when demand and electricity prices are higher.
Bistrica’s strategic value will therefore lie primarily in energy storage, power system balancing and the easier integration of new wind and solar power capacity.
According to JICA’s official project description, the project is intended to address fluctuations in electricity supply and demand and help stabilise Serbia’s power grid.
A total of 245 applications submitted for permits and approvals
So far, 245 applications have been submitted to the relevant institutions for different conditions, permits and approvals. Some of the procedures were completed over the past six months, but a significant volume of work remains for the coming period.
Four urban planning projects have been approved, providing what the Ministry described as the complete planning basis required for the investment.
Eight sets of location conditions have been obtained, while another six are being processed and are expected to be completed by the end of September.
Six decisions declaring public interest for expropriation have also been adopted, enabling the resolution of property and legal issues concerning the plots covered by the planning documents.
Designs for the main system submitted for review
The preliminary designs for the main system and the grid connection switchyard have been completed and submitted to the State Review Commission.
Another 11 preliminary designs are nearing completion and should be submitted for review by the end of 2026. The preliminary designs and the documentation required for the construction permit are being prepared simultaneously.
Under the current schedule, the conditions for issuing the construction permit for the main plant are expected to be met in early 2027.
Preparatory works are expected to begin earlier, in the coming months. However, an important distinction must be made: the construction tender for the main plant has not yet been launched. It is planned for 2027.
JICA loan agreement expected during EXPO 2027
The project is being prepared in cooperation with JICA, whose requirements and procedures will also have to be followed during the tender process.
The loan agreement with the Japanese agency is expected to be signed during the specialized EXPO 2027 exhibition in Belgrade. The financing arrangement has therefore not yet been formally concluded, but its signing is planned for next year.
JICA is also preparing the project’s environmental and social impact assessment. One of the issues that still needs to be resolved concerns the disposal of material excavated during construction.
ECI