Greenvolt begins construction of 600 MW / 2.4 GWh battery storage system in Poland

September 29, 2026

Greenvolt Group has started construction of the 600 MW / 2.4 GWh Siedlce battery energy storage system in Poland, a project which, according to the company, will become the largest BESS in Poland and one of the largest battery storage facilities in Europe.

The project is being developed by Greenvolt Power, Greenvolt Group’s utility-scale renewable energy division, and is expected to enter commercial operation by the end of 2027.

With four hours of storage duration, Siedlce is designed to support the integration of renewable energy, provide flexibility to the Polish electricity system and help balance fluctuations between electricity generation and consumption.

210 battery containers and 105 transformer units

The Siedlce project will comprise 210 battery containers and 105 transformer containers equipped with power conversion systems (PCS).

Greenvolt has selected BYD Energy Storage technology for the project, while Greenvolt Power is working with P&Q and ONDE on the electrical infrastructure required for the facility.

With an energy storage capacity of 2.4 GWh, the system will be capable of delivering its full 600 MW output for approximately four hours.

The scale of the project reflects the rapid development of battery storage in Poland as the country adds increasing volumes of renewable generation and seeks greater flexibility across its electricity system.

Greenvolt is building a 1 GW / 4 GWh battery portfolio in Poland

Siedlce is not Greenvolt’s first large-scale battery project in the Polish market.

In July 2026, the company inaugurated the Turośń Kościelna battery storage facility, with a capacity of 200 MW / 800 MWh.

Another 200 MW / 800 MWh battery project in Ełk is expected to become operational in the fourth quarter of 2026.

Together, the three projects represent 1 GW of power and 4 GWh of battery storage capacity.

Greenvolt has positioned Poland as one of its key European markets for battery storage. The company has a probability-weighted BESS pipeline of approximately 4.6 GW, of which around 2.4 GW is located in Poland.

The expansion of storage is taking place alongside Greenvolt’s broader investment in renewable energy in the country. The group has announced plans to invest approximately €800 million in renewable energy projects in Poland by the end of 2026.

The 600 MW / 2.4 GWh Siedlce project therefore represents more than another large battery facility. It is part of a broader shift in Poland’s electricity system towards infrastructure capable of integrating increasing volumes of variable renewable generation while providing additional flexibility and balancing capacity.