Enery has integrated its 601.8 MWh Nova Zagora battery energy storage system into Volue’s trading platform, enabling one of the largest battery storage facilities in Central and Eastern Europe to actively participate across several segments of the electricity market.
Located in southeastern Bulgaria, the battery system has a power capacity of 150 MW and an energy storage capacity of 601.8 MWh. It has now been integrated into Enery’s existing portfolio managed through the Volue Trading Suite.
The development does not mark the commissioning of a new battery. Nova Zagora has been operational since March 2026 and was officially inaugurated in May. The latest step is its integration into an automated system for trading and optimisation across multiple electricity markets.
From day-ahead trading to ancillary services
The integration enables the battery to participate in the day-ahead and intraday markets, as well as markets for ancillary services. The platform combines forecasting, trading, scheduling and physical battery control.
This allows Enery to optimise the operation of the storage system in response to different market signals, rather than using the battery for a single service or revenue stream.
This type of operation is becoming increasingly important as electricity generation from wind and solar power grows. Batteries can absorb electricity during periods of high generation and low prices and return it to the system when demand and prices are higher or when additional grid flexibility is required.
150 MW of power and 601.8 MWh of storage
Nova Zagora is a standalone battery energy storage system comprising 120 containers, each with a storage capacity of 5.015 MWh. The facility also has its own 33/110 kV substation.
The project was developed in less than a year. Sunotec served as the EPC contractor, while Sungrow supplied the battery technology. Financing involved DSK Bank and a partnership with Vitol, while the project also received support through Bulgaria’s RESTORE programme under the Recovery and Resilience Plan.
According to Enery, the battery is designed to provide balancing services, increase the flexibility of the electricity system and support greater integration of renewable energy sources.
Batteries are becoming active market assets
The next stage in the development of large-scale battery storage in Southeast Europe is no longer simply about adding more MWh of storage capacity. How these assets are operated and which electricity markets they can access are becoming increasingly important.
At Nova Zagora, the combination of 150 MW of power and 601.8 MWh of storage gives the facility both a commercial and a system-level role.
As variable renewable generation expands across the region, such systems could play an increasingly important role in balancing the grid, reducing constraints on the integration of new renewable capacity and taking advantage of electricity price differences throughout the day.