Slovenian energy group GEN-I is expanding its cooperation with SUNOTEC in Bulgaria following the successful start of commercial management of the Brusartsi BESS, with a power capacity of 150 MW and an energy storage capacity of 379 MWh.
The project follows the earlier launch of the Byala Slatina BESS, with a capacity of 50 MW / 126 MWh. The two systems, developed and built by SUNOTEC, have a combined power capacity of 200 MW and a storage capacity of 505 MWh, and are connected to the Bulgarian electricity grid.
GEN-I is responsible for the commercial management and market optimisation of the systems, including their participation in the day-ahead and intraday electricity markets, as well as ancillary services markets.
The partnership is set to expand further. GEN-I and SUNOTEC have also agreed on nine additional BESS projects in Bulgaria, with a combined power capacity of 195 MW and storage capacity of 782 MWh, which are expected to enter commercial operation within the next 12 months.

GEN-I already has its own investments in Bulgaria
In addition to managing SUNOTEC’s projects, GEN-I also has its own investment presence in the Bulgarian market. In June 2026, GEN-I Invest completed the acquisition of three battery storage systems Belovo, Momchilgrad and Parvomay 1 with a combined power capacity of 30 MW and storage capacity of 76 MWh.
The group is also present in the country through GEN-I Sofia – Electricity Trading and Sales, its local company for electricity trading and sales. GEN-I already has investment experience elsewhere in the region as well, including two large solar power plants in North Macedonia with a combined capacity of 29 MW.