Serbia’s Minister of Mining and Energy in a caretaker capacity, Dubravka Đedović Handanović, announced that the installation of the first pipes for the gas interconnector between Serbia and North Macedonia will begin during the week of 12 October.
The interconnector will have a planned capacity of approximately 1.5 billion cubic metres of natural gas per year. Its construction will provide an additional connection between the gas transmission systems of Serbia and North Macedonia, as well as access to new supply sources through Greece and the wider infrastructure of the Vertical Gas Corridor.
The start of construction was announced following a meeting of the energy ministers of Serbia, North Macedonia, Greece and Bulgaria, held on 6 October in Belgrade. Serbian Minister of Mining and Energy Dubravka Đedović Handanović further announced that work on the first five kilometres of the pipeline is expected to begin this week.
Serbian section to span 145 kilometres, with completion expected in 2028
According to information from Serbian institutions, the new pipeline will start in Orljane, pass through Leskovac and Vranje, and terminate at the border with North Macedonia.
The Serbian section is planned to extend approximately 145 kilometres, while the investment is estimated at around €153 million, according to earlier assessments.
Most construction activities are expected to take place during 2027 and the first half of 2028. Previous announcements indicated that the interconnector would be completed in 2027, but the latest information from Belgrade suggests a longer implementation period for the Serbian section.
North Macedonia to gain a significant role in the Vertical Gas Corridor
The Serbia–North Macedonia gas interconnector is closely linked to the construction of the new pipeline between Greece and North Macedonia, which is expected to provide access to additional natural gas supplies from the south.
According to the joint ministerial statement issued on 6 October, the Greek section of the Greece–North Macedonia interconnector is expected to be completed by the end of 2026, while completion of the North Macedonian section is planned for 2027.
Once both projects are connected, the infrastructure will enable natural gas to be transported from Greece through North Macedonia to Serbia, including liquefied natural gas (LNG) delivered through the Alexandroupolis terminal.
According to the joint ministerial statement, the export capacity of the relevant gas infrastructure in Greece is expected to reach approximately 9.5 billion cubic metres per year by 2027, creating additional supply opportunities for countries across the region.
New supply routes and greater energy security
One of the most important benefits of the new interconnector is the opportunity to diversify natural gas supply sources and transportation routes.
For Serbia, the project will provide an additional connection to southern gas markets, complementing its existing interconnector with Bulgaria. For North Macedonia, connections with Greece and Serbia will create opportunities for greater system flexibility and expanded regional natural gas trading.
The new infrastructure could also contribute to increased competition among suppliers. However, its impact on gas prices will depend on supply availability, transmission tariffs, commercial agreements and developments in international energy markets.
Harmonising transmission capacities and tariff systems among gas transmission system operators will be particularly important to ensure that the new interconnectors provide economically competitive natural gas transportation.
As part of broader regional cooperation, the long-term possibility of adapting sections of the gas infrastructure for hydrogen transportation is also being considered, in line with European energy transition policies.