The 154 MW Čibuk 2 wind farm has officially begun operations in Serbia. Together with the neighbouring Čibuk 1 facility, it forms the largest wind power complex in Serbia and the Western Balkans, with a combined installed capacity of 312 MW.
Čibuk 2 is located in the South Banat region, in the municipality of Kovin, around 40 kilometres from Belgrade. The project was developed by UAE-based Masdar and Finnish renewable energy fund manager Taaleri Energia.
Electricity for around 80,000 households
The new wind farm consists of 22 Nordex turbines. It is expected to generate up to 336,000 MWh of electricity annually, equivalent to the consumption of around 80,000 households.
According to the investors, Čibuk 2 will avoid approximately 311,200 tonnes of carbon dioxide emissions each year. More than 1,000 people were involved during construction, including workers, subcontractors and project management teams, with the majority coming from the South Banat region.
More than €500 million invested
Čibuk 2 is located next to the 158 MW Čibuk 1 wind farm, which has been operational since 2019. The two projects share the same grid connection point.
Combined investment in the Čibuk complex exceeds €500 million. Together, the two wind farms can generate enough clean electricity to meet the needs of approximately 178,800 households.
According to Serbia’s Ministry of Mining and Energy, Čibuk 1 and Čibuk 2 together account for around one quarter of the country’s combined installed wind and solar power capacity.
Masdar plans an additional 200 MW
Masdar has announced a development pipeline of more than 200 MW in Serbia, covering wind and solar power projects as well as battery energy storage systems.
Serbia plans to bring around 3.5 GW of new wind and solar capacity online by 2030 and increase the share of renewables to 45% of national electricity generation.
ECI