The Romanian Energy Regulatory Authority, ANRE, has issued the final regulatory approval required before construction can begin on the first phase of Dama Solar, a planned solar complex with a capacity of approximately 1.2 GW in Arad County, western Romania.
The decision was adopted by ANRE’s Regulatory Committee at its meeting on 11 August, approving an application submitted by West Power Investments for the construction of the new CEF Arad 1 energy facility.
West Power Investments is the special-purpose company through which Rezolv Energy is developing Dama Solar in the municipalities of Pilu and Grăniceri, close to the Romanian-Hungarian border.
Romanian sources specify that the approval covers the first phase rather than the entire complex. It represents the final key regulatory document before the approved part of the project can proceed towards financing and physical implementation.
From 1,044 MW to approximately 1.2 GW
Dama Solar was initially presented as a project with an installed capacity of 1,044 MW. Following further design optimisation and the application of newer technology, Rezolv Energy now lists the planned capacity at approximately 1.2 GW.
The entire complex is expected to cover more than 1,064 hectares. According to the developer’s estimates, its annual electricity production could match the consumption of more than 280,000 households, or almost one million people.
If completed according to the current plan, Dama Solar would become the largest operational solar power plant in the European Union.
State-backed price secured for 520 MW
The project secured support for a total capacity of 520 MW in Romania’s second contracts-for-difference auction, held in 2025.
The capacity was divided into two blocks of 260 MW, with a bid price of approximately €42.20/MWh. This means that CfD support covers less than half of Dama Solar’s total planned capacity. The developer will need to secure other market arrangements for the remaining electricity output, including long-term power purchase agreements – PPAs.
The CfD mechanism provides a long-term reference price for the electricity generated, thereby reducing market exposure for the supported portion of the investment.
Financing has not yet been closed
Although the approval represents a significant regulatory milestone, it does not mean that construction of the entire complex will begin automatically.
Rezolv Energy says that financing and equipment procurement procedures are continuing, while physical construction is expected to begin after the project reaches financial close.
According to project documentation published by IFC in April 2026, the investment is estimated at approximately €520 million, while the financial institution is considering providing an A Loan of up to €107 million for its own account.
Battery storage also planned
Dama Solar may also include a large-scale battery energy storage system. Its final power and storage capacity have not yet been officially confirmed in the latest project announcement.
The batteries would allow part of the solar generation to be shifted to periods of higher electricity demand and would improve the flexibility required to connect such a large generation facility to Romania’s electricity system.
The project also envisages an 82-hectare nature reserve, alongside plans to return part of the land to pasture and use it for agricultural activities.
The key test still lies ahead
ANRE’s approval brings Dama Solar closer to implementation, but the most important steps are still ahead: closing the financing package, securing contracts for the remaining electricity output, procuring the necessary equipment and building the grid connection infrastructure.
ANRE’s approval covers CEF Arad 1, the first phase of Dama Solar. The project’s investor, Rezolv Energy, expects to reach financial close soon, after which construction is expected to begin, with commissioning planned for 2028.