Wind Park Korita in Montenegro receives construction permit

October 15, 2026

Vjetro park Korita has received a construction permit for the first phase of the Korita wind farm, with an installed capacity of 88 MW, in the municipality of Bijelo Polje, Montenegro. The permit was issued on 2 October 2026 by the Ministry of Spatial Planning, Urbanism and State Property, with the information published on 14 October.

The project includes the construction of 11 wind turbines, supporting infrastructure and a 35/400 kV substation. Obtaining the permit removes one of the main administrative obstacles to the project’s development.

First phase includes 11 wind turbines

According to the project documentation, the first phase of the Korita wind farm will have a total installed capacity of 88 MW.

The planned turbines will have a hub height of 110 metres and a rotor diameter of 171 metres, with blades measuring 83.9 metres in length.

The project also includes a 35/400 kV substation to facilitate the connection of the wind farm to the high-voltage electricity transmission network.

The wind farm will be located in the Korita area, within the municipality of Bijelo Polje in northern Montenegro.

Grid connection agreement secured earlier this year

In June 2026, Montenegro’s transmission system operator, CGES, signed a grid connection agreement for the Korita wind farm.

The agreement was an important prerequisite for advancing the construction approval process. An earlier application for a construction permit had been rejected in June because certain administrative requirements had not been met, including those related to grid connection.

With the permit issued in October, the project has obtained the necessary construction authorisation to proceed with the next stages of development.

However, receiving a construction permit does not necessarily mean that construction activities have already started.

Investment estimated at approximately €132 million

According to previously published project information, the investment is estimated at approximately €132 million.

The planned wind farm represents a significant addition to Montenegro’s renewable energy capacity as the country seeks to diversify its electricity generation mix and expand domestic renewable production.

The project’s implementation will depend on the organisation of construction activities, procurement and installation of turbines, and completion of the necessary electricity infrastructure.

Earlier project information identified 2030 as an indicative commissioning date. However, the newly issued construction permit does not itself confirm a final completion schedule.