EDF power solutions North America has secured financing for Utah Solar 1, a major solar PV project in the US state of Utah, allowing the project to move into full-scale construction.
Located in Millard County, the project will have an installed capacity of 394 MWdc, or 300 MWac, with electricity deliveries scheduled to begin in mid-2027.
The project also stands out because electricity generated in Utah will ultimately serve customers in Los Angeles under a long-term power purchase agreement.
766,000 MWh of electricity per year
Utah Solar 1 is expected to generate approximately 766,000 MWh of electricity annually.
The project has a 30-year power purchase agreement with the Southern California Public Power Authority (SCPPA), with the electricity destined for customers of the Los Angeles Department of Water and Power (LADWP).
According to an earlier estimate from EDF, the project’s expected annual generation is equivalent to the annual electricity consumption of approximately 126,800 average California homes.
The solar PV facility will be constructed on state-owned land managed by the Utah Trust Lands Administration.
Five banks finance the project
The financing was secured through credit facilities provided by Crédit Agricole CIB, MUFG Bank, National Bank of Canada, Société Générale and Standard Chartered Bank.
MUFG serves as administrative agent, while Crédit Agricole CIB acts as initial coordinating lead arranger. The financing package also includes a tax credit bridge facility linked to US Production Tax Credits expected to be generated by the project.
EDF did not disclose the total value of the financing.
Financial close represents a major milestone for Utah Solar 1, enabling the project to proceed with full-scale construction ahead of the planned start of electricity deliveries in 2027.
Around 400 workers during construction
At peak construction, the project is expected to employ approximately 400 workers.
Over its multi-decade operating life, EDF estimates that Utah Solar 1 will generate more than $40 million in local tax revenue for Millard County.
An additional $27 million in lease revenue is expected to be generated for the Utah Trust Lands Administration, which manages the land on which the project will be built.
Utah Solar 1 also illustrates the growing geographic integration of the US electricity system. A major generation facility will be built in Utah, while its output, secured through a 30-year agreement, will ultimately serve customers of LADWP in Los Angeles.
ECI