The French Development Agency – AFD has provided a grant of €500,000 to support the development of the professional, human-resource and organizational capacities required for the preparation of Serbia’s nuclear programme.
The support was formalised through a partnership agreement between the Republic of Serbia, AFD and French electricity utility EDF, signed by Minister of Mining and Energy Dubravka Đedović Handanović.
The funds will be directed towards the preparation, development and management of the first phase and part of the second phase of Serbia’s nuclear programme. A key priority will be the preparation of a human resources development strategy, as one of the fundamental prerequisites for establishing a national nuclear programme.

This includes identifying and developing domestic engineers, physicists, technicians, legal experts and other professionals, as well as strengthening the institutions that will be responsible for planning, coordinating and regulating the future use of nuclear energy.
EDF Has Already Prepared the Initial Roadmap
The new financial support from AFD builds on the cooperation that Serbia has already established with EDF.
A consortium of French companies led by EDF prepared the Preliminary Technical Study on the Peaceful Use of Nuclear Energy. The study was officially presented in March 2026 and provided the initial roadmap for the development of Serbia’s nuclear programme.
The document is aligned with the approach of the International Atomic Energy Agency – IAEA and covers the 19 nuclear infrastructure issues that a country must address before proceeding with the construction of a nuclear power plant.
These include the legislative and regulatory framework, nuclear safety, human resources development, financing, technology and site selection, connection to the electricity transmission grid, nuclear fuel and waste management, and opportunities for the participation of domestic industry.
According to the latest official information, EDF is expected to prepare three additional studies during the first phase, while the remaining 14 studies will be subject to discussions with other international companies experienced in the development of nuclear programmes.
A previous announcement by the Serbian Ministry stated that EDF would work on four additional studies. The difference most likely stems from the fact that the human resources strategy, supported through the AFD project, had previously been included among those four studies.
Initial Decision Expected by Mid-2027
The agreement with AFD comes at a time when Serbia has already defined a specific timeline for its nuclear programme.
The objective is to complete the first phase by mid-2027 and prepare all the information required for the government to make an informed decision on whether and how to proceed with the development of nuclear energy.
The first phase does not involve a final decision to build a power plant. It is intended to assess the programme’s justification, establish the basic institutional and legislative framework, and prepare analyses covering technology, financing, location, grid integration and human resources.
By 2032, Serbia plans to be institutionally, regulatorily and professionally prepared to select a technology and enter the project contracting and development process. The Ministry’s ambition is for construction to begin by 2035, with the possibility of a nuclear power plant being connected to the grid around 2040.